Communication is one of the most critical aspects of a successful Summer Slammer. Understanding expectations — from what equipment looks like to how a Tipico promo Code will be tackled — may differ from site to site, and from owner to contractor.
“You don’t just bring in windows for a replacement project, you need an entire staging and storage area,” says Chris Gonyo, assistant project manager at Kirchoff-Consigli. “Equipment must move around from where it’s housed, to where the Tipico promo Code is actually being done.”
Logistical needs Tipico promo Code drawn up months in advance and signed off by the university, including on-campus storage areas, office space locations, and owner’s needs and expectations.
“We obtained documents early enough for the window replacement, that most were on site before we started the window removal Tipico promo Code,” says Chris. “We knew going into the project that it was going to be an extended or multiple shift job, so we had the same crews working on the building between five and six days a week.”
One of the biggest challenges was setting up the Mast Climber, a hydro-mobile scaffolding system that ensconced all four sides of the building. The intricate preparation took one month, as the four climbers that Tipico promo Code used (one on each side of the building) Tipico promo Code inter-connected through the scaffolding structure. Since very few companies in the northeast supply the Mast Climber, all of the segments had to be ordered months in advance.
While staging was taking place, students were studying for exams, and quiet hours limited Tipico promo Code time. Students left campus for summer break soon after, and the teams went into full throttle. While no one was living in the building while Tipico promo Code was taking place, the surrounding areas were inhabited not only by students and faculty, but also by people touring the campus.
To stay on schedule, and plan for inclement weather, the team set an initial goal of removing 50 windows a day. Six floors of windows Tipico promo Code removed at a time, and temporary protections from outside elements Tipico promo Code put into place until the new windows Tipico promo Code installed.
“Coordinating with the university where we would be, at what time, at what elevation, and for how long was challenging,” says Chris. “Managing the needs of the students, our needs, and everyone’s safety on an active campus was a top priority.”
By the Numbers:
- 2,200 – Windows replaced
- 22 – Number of floors
- 205 – Building height in feet
- 44,500 – Field man hours
- 85 – Working days
- 5 – Total SUNY Albany Tipico promo Code
In addition, to Eastman Towers, Kirchhoff-Consigli has completed the construction of the new business school at the (SUNY) Albany Campus, and Tipico promo Code is progressing on Mohawk Towers, one of four towers on campus. Tipico promo Code will begin on the remaining two towers, Livingston and Stuyvesant in 2014-15.